Project Plan: Food Order Bot Enhancements and Production Readiness
Startup Team: 4 Engineers (Frontend, Backend, LLM/AI, DevOps/Testing)
Duration: 8 Weeks (February 22, 2025 – April 19, 2025)
Objective:
Enhance the Food Order Bot, resolve known issues, and prepare for a production launch.
Assumptions:
- Engineers work 40 hours/week, with a 20% buffer for unforeseen issues.
- Each engineer focuses on their expertise but collaborates on critical tasks.
- Access to necessary tools (Git, Python, Mistral API, Gradio, FastAPI) and hardware.
- Weekly syncs (1 hour) for planning and progress tracking.
Goals:
- Ambitious but Realistic: Launch a production-ready Food Order Bot with multi-city support, rate limiting, order history, and improved UI/UX within 8 weeks.
- Clear and Achievable: Each milestone builds on the previous, ensuring steady progress and quality.
Detailed Plan
Week 1: Planning and Setup (February 22 – February 28, 2025)
Deliverables:
- Finalize project scope and requirements document (based on Spec 4).
- Set up development environment, version control (Git), CI/CD pipeline (GitHub Actions).
- Update
requirements.txt
and ensure all dependencies are installed.
- Conduct initial code review and refactor for clarity.
Milestone:
- Project Kickoff and Environment Ready
Engineer Roles:
- All Engineers: Collaborate on planning and setup (8 hours each).
- DevOps/Testing: Set up CI/CD pipeline (16 hours).
Timeline:
Week 2–3: Core Enhancements (March 1 – March 14, 2025)
Deliverables:
- Order History Feature:
- Backend: Add
/orders/history
endpoint in mock_server.py
and db.py
for retrieving past orders.
- Frontend: Implement Gradio command to show order history in
gradio_client.py
.
- Rate Limiting and Quotas:
- Backend: Implement rate limiting using
fastapi-limiter
or custom middleware in mock_server.py
(e.g., 100 requests/hour per user).
- Testing: Unit tests for rate limiting and order history.
Milestone:
- Core Features Implemented
Engineer Roles:
- Backend Engineer: Order history endpoint and rate limiting (40 hours total over 2 weeks).
- Frontend Engineer: Gradio UI updates (30 hours total over 2 weeks).
- LLM/AI Engineer: Review LLM tool calls for order history compatibility (20 hours total over 2 weeks).
- DevOps/Testing: Write tests and set up CI/CD for new features (40 hours total over 2 weeks).
Timeline:
Week 4–5: Multi-City Support and Data Expansion (March 15 – March 28, 2025)
Deliverables:
- Multi-City Support:
- Update
restaurants.json
to include “city” for each restaurant (e.g., New York, Los Angeles, Bengaluru).
- Enhance
order_processor.py
and llm.py
to filter restaurants by city dynamically.
- Data Expansion:
- Add sample restaurant data for other cities (e.g., 5 restaurants per city).
- Update
filter_restaurants_by_city
in order_processor.py
to handle multi-city logic.
Milestone:
- Multi-City Support Complete
Engineer Roles:
- Backend Engineer: Update
db.py
and order_processor.py
for multi-city (40 hours total over 2 weeks).
- LLM/AI Engineer: Refine
llm.py
tools for city-specific queries (30 hours total over 2 weeks).
- Frontend Engineer: Update Gradio to display city selection (20 hours total over 2 weeks).
- DevOps/Testing: Test multi-city logic and data integrity (40 hours total over 2 weeks).
Timeline:
Week 6–7: UI/UX Improvements and Bug Fixes (March 29 – April 11, 2025)
Deliverables:
- Gradio Formatting Fix:
- Resolve
\n
rendering issue in gradio_client.py
using HTML or split-line approach.
- Ensure line breaks appear correctly for menu, order summary, etc.
- Bug Fixes:
- Address any remaining tool call issues (e.g., price filtering in Rs).
- Fix any performance or stability issues identified during testing.
Milestone:
- UI/UX Polished and Bugs Fixed
Engineer Roles:
- Frontend Engineer: Gradio formatting fix (40 hours total over 2 weeks).
- Backend Engineer: Bug fixes in
mock_server.py
and order_processor.py
(30 hours total over 2 weeks).
- LLM/AI Engineer: Adjust
llm.py
for price filtering (20 hours total over 2 weeks).
- DevOps/Testing: Comprehensive testing and performance tuning (40 hours total over 2 weeks).
Timeline:
- March 29–April 11 (2 weeks)
Week 8: Production Readiness and Deployment (April 12 – April 19, 2025)
Deliverables:
- Production Deployment:
- Deploy FastAPI server to a cloud provider (e.g., AWS, GCP) with Docker.
- Configure Gradio for public access with
share=True
.
- Documentation Update:
- Update Spec 4 and add user manuals, API docs (OpenAPI/Swagger).
- Final Testing and Launch:
- Conduct end-to-end testing with real users.
- Launch the Food Order Bot publicly.
Milestone:
Engineer Roles:
- DevOps/Testing: Deployment and final testing (40 hours total over 1 week).
- Backend Engineer: Dockerize and configure server (30 hours total over 1 week).
- Frontend Engineer: Public Gradio setup (20 hours total over 1 week).
- LLM/AI Engineer: Final LLM tuning (10 hours total over 1 week).
Timeline:
Mermaid Gantt Chart
Below is a Mermaid Gantt chart representing the timeline and milestones. You can paste this into a Markdown viewer or Mermaid live editor (e.g., Mermaid Live Editor) to visualize it.
gantt
title Food Order Bot Development Timeline (Feb 22 - Apr 19, 2025)
dateFormat YYYY-MM-DD
axisFormat %b %d
section Planning and Setup
Project Kickoff & Environment Ready :done, 2025-02-22, 1w
section Core Enhancements
Order History Feature :active, 2025-03-01, 2w
Rate Limiting and Quotas :2025-03-01, 2w
section Multi-City Support
Multi-City Support Complete :2025-03-15, 2w
section UI/UX Improvements
UI/UX Polished and Bugs Fixed :2025-03-29, 2w
section Production Readiness
Production Launch :2025-04-12, 1w
Key Milestones and Deadlines:
- February 28, 2025: Project Kickoff and Environment Ready – All tools, repositories, and environments set up.
- March 14, 2025: Core Features Implemented – Order history and rate limiting complete.
- March 28, 2025: Multi-City Support Complete – Multi-city functionality and data expansion finalized.
- April 11, 2025: UI/UX Polished and Bugs Fixed – Gradio formatting fixed, bugs resolved.
- April 19, 2025: Production Launch – System deployed to production, tested, and launched publicly.
Engineer Allocation and Collaboration:
- Week 1: All engineers collaborate on planning (20% of time), with DevOps/Testing leading CI/CD setup.
- Weeks 2–7: Engineers focus on their specialties but pair for cross-functional tasks (e.g., Backend/LLM for tool calls, Frontend/DevOps for testing).
- Week 8: DevOps/Testing leads deployment, with all engineers contributing to final testing and documentation.
Ambitious but Realistic Goals:
- Launch a Production-Ready Product: Deploy a scalable, user-friendly Food Order Bot within 8 weeks, supporting multi-city operations and advanced features.
- Maintain Code Quality: Achieve 100% linting compliance and consistent formatting, with automated testing covering 80% of functionality.
- User Experience: Ensure 95% of user queries (e.g., login, ordering, city filtering) are handled correctly via LLM tool calls.
- Scalability: Handle 1,000 concurrent users with rate limiting and SQLite optimization.
Notes:
- Risks: Delays in LLM API response times, Gradio UI issues, or third-party API downtime could push timelines. Buffer 20% extra time for each milestone.
- Tools: Use Git for version control, Slack for communication, and Jira/Trello for task tracking.
- Testing: Weekly integration tests by DevOps/Testing, with final user testing in Week 8.