Project Plan: Food Order Bot Enhancements and Production Readiness

Startup Team: 4 Engineers (Frontend, Backend, LLM/AI, DevOps/Testing)

Duration: 8 Weeks (February 22, 2025 – April 19, 2025)

Objective:

Enhance the Food Order Bot, resolve known issues, and prepare for a production launch.

Assumptions:

Goals:

Detailed Plan

Week 1: Planning and Setup (February 22 – February 28, 2025)

Deliverables:

Milestone:

Engineer Roles:

Timeline:

Week 2–3: Core Enhancements (March 1 – March 14, 2025)

Deliverables:

Milestone:

Engineer Roles:

Timeline:

Week 4–5: Multi-City Support and Data Expansion (March 15 – March 28, 2025)

Deliverables:

Milestone:

Engineer Roles:

Timeline:

Week 6–7: UI/UX Improvements and Bug Fixes (March 29 – April 11, 2025)

Deliverables:

Milestone:

Engineer Roles:

Timeline:

Week 8: Production Readiness and Deployment (April 12 – April 19, 2025)

Deliverables:

Milestone:

Engineer Roles:

Timeline:

Mermaid Gantt Chart

Below is a Mermaid Gantt chart representing the timeline and milestones. You can paste this into a Markdown viewer or Mermaid live editor (e.g., Mermaid Live Editor) to visualize it.

gantt
    title Food Order Bot Development Timeline (Feb 22 - Apr 19, 2025)
    dateFormat  YYYY-MM-DD
    axisFormat %b %d

    section Planning and Setup
    Project Kickoff & Environment Ready :done, 2025-02-22, 1w

    section Core Enhancements
    Order History Feature            :active, 2025-03-01, 2w
    Rate Limiting and Quotas         :2025-03-01, 2w

    section Multi-City Support
    Multi-City Support Complete      :2025-03-15, 2w

    section UI/UX Improvements
    UI/UX Polished and Bugs Fixed    :2025-03-29, 2w

    section Production Readiness
    Production Launch                :2025-04-12, 1w

Key Milestones and Deadlines:

Engineer Allocation and Collaboration:

Ambitious but Realistic Goals:

Notes: